Lodge Room Renovations are Underway

Updated: May 27, 2022

Preparations began on May 25th for the installation of the new tile floor in the lodge room. The first step was to remove all the furniture, which you can see in progress in the pictures. The next step will be to remove the carpet and prepare the floor for the tiles.


We're hoping the new tiles will be in place by the end of May then we'll get them waxed and buffed by June 7th, then move all the furniture in and set everything up to have the lodge ready to use in time for our June meeting.


Keep checking back for more progress updates.


Altar removed. Pews are next!


Pews are heading out the door.